Procedures for mooring operations#
Note
Based on (translated and slightly modified by ΓF) the document PROSEDYRE FOR RIGGARBEID PΓ
F/F KRONPRINS HAAKON written by senior engineer Kristen Fossan (29.06.2018).
Mooring: Instrument-carrying construction of length 1-3000 m that is lowered to the sea floor and held in place there by a metal or concrete weight denoted an anchor.
Mooring deployments#
Anchor-first deployments#
Advantages
The mooring can be pulled up and adjusted to the desired target depth.
Only a small hole in the ice is required if deploying in ice.
The vessel can remain stationary.
Drawbacks
The mooring line must be able to carry the full weight of the mooring.
Procedure#
Kevlar or other material constituting the mooring line is spooled onto a winch strong enough to carry the weight of the anchor.
Pieces of chain are be inserted where instruments will be placed (AWI shackle / ring shackle).
All elements that will be attached to the mooring (instruments, floats, etc) are laid out on deck.
Toolbox meeting with all involved parties before starting deployment.
The anchor (or the anchor plus the first group) is lowered into the deep until the first chain appears.
The lower half of this chain is shackled to the side of the vessel or to another winch.
The chain is opened and the desired instrument group is shackled to kevlar and lifted up using the main crane.
The mooring is further lowered until the next chain appears, and the process is repeated.
When the entire mooring is out, an acoustic release is attached to the top of the mooring. The mooring is then lowered until the anchor hits the bottom.
If the depth is correct, the release is opened and the mooring deployment is complete.
If the depth is wrong, the mooring is lifted from the sea floor, and either the mooring length is adjusted or the ship moves to a different location with different bottom depth.
The position of the mooring is noted on mooring diagram along with all details.
Anchor-last deployments#
Advantages
The mooring line does not have to be able to carry the full weight of the mooring.
Drawbacks
The vessel must either move or use a small boat or similar to extend the mooring.
No possibility of adjusting mooring depth after deployment.
Procedure#
Kevlar or other material constituting the mooring line is spooled onto a winch strong enough to carry the weight of the drag of the mooring in water.
The top of the mooring is attached t the mooring line and liften into the ocean.
Kevlar is paid out until the next instrument group is to be attached.
The mooring is shackled to the ship and instruments are attached to the mooring line. Pull in a little so that the shackle can be loosened and then pay out until the next instrument group.
Repeat until only the anchor and release is left.
When only the anchor and release are left on deck, these are shackled to the mooring. Typically, a second release is used to lift the anchor and mooring release and lower them into the water.
Now, the vessel moves to the desired location, and the second/upper release is triggered to drop the mooring.
The anchor will fall approximately vertically and drag the rest of the mooring along with it - like a diving sea snake.
Mooring recoveries#
Procedure#
The ship moves to the assumed location of the mooring.
Try to locate the mooring (using the release transponder and ideally also an echosounder or similar).
Assess whether the mooring looks ok.
Position the vessel in the desired position in relation to the mooring.
A good rule of thumb is that the mooring should be 200 m from the bridge at a 45 degree angle.
The mooring can be long, so be careful of getting tangled in the propellers!
Activate the release.
If all is ok, the mooring will release and appear at the surface after a time period depending on buoyancy and depth.
If the mooring floats do not appear, the mooring must be dredged up.
This is usually a good approach, but there is greater risk of damaging equipment.
Attach to the top of the mooring and bring the mooring on deck.
The instrument groups are unshackled and cleaned before they are brough inside for servicing.
The kevlar is spooled onto the winch.
Trawl-safe bottom landers#
Metal shell with buoyancy that protects the instruments and acoustic release. Kept down by metal- or concrete frame.
Typically deployed by lowering down to the sea floor and releasing.
Recovery:
Acoustic release is activated.
The frame should pop up when released from the weight as it is positively buoyant.
Concrete frames are usually left on the bottom. Metal frames are typically recovered.